Offshore Wind Farms On-Site Submarine Cable Testing and Diagnosis with Damped AC
The current power cables IEC standards do not provide adequate recommendations for after-laying testing and diagnosis of offshore export and inter-array power cables. However the standards IEEE 400 and IEEE 400.4 recommend partial discharge monitored testing, e.g., by continuous or damped AC voltages (DAC). Based on the international experiences, as collected in more than 20 years at different power grids, this contribution focuses on the use of DAC for after-laying testing and diagnosis of submarine power cables both the export and inter-array cables. Higher risk of failure, long unavailability, higher repair costs, and maintenance costs imply that advanced quality control is becoming more important. The current state of the existing and drafting international standards are based on onshore experiences and not related to the actual serious problems experienced with failures on export up to 230 kV and inter-array cables up to 66 kV. The application of damped AC as a testing solution in this concern is specially discussed. The advantages of this testing technique, in combination with actual testing examples, show the findings on export and inter-array cables at offshore wind farms.
Original Text (This is the original text for your reference.)
Offshore Wind Farms On-Site Submarine Cable Testing and Diagnosis with Damped AC
The current power cables IEC standards do not provide adequate recommendations for after-laying testing and diagnosis of offshore export and inter-array power cables. However the standards IEEE 400 and IEEE 400.4 recommend partial discharge monitored testing, e.g., by continuous or damped AC voltages (DAC). Based on the international experiences, as collected in more than 20 years at different power grids, this contribution focuses on the use of DAC for after-laying testing and diagnosis of submarine power cables both the export and inter-array cables. Higher risk of failure, long unavailability, higher repair costs, and maintenance costs imply that advanced quality control is becoming more important. The current state of the existing and drafting international standards are based on onshore experiences and not related to the actual serious problems experienced with failures on export up to 230 kV and inter-array cables up to 66 kV. The application of damped AC as a testing solution in this concern is specially discussed. The advantages of this testing technique, in combination with actual testing examples, show the findings on export and inter-array cables at offshore wind farms.
+More
quality control partial discharge monitored testing afterlaying testing and diagnosis of offshore export and interarray power continuous or damped ac voltages solution interarray cables failure dac
APA
MLA
Chicago
Edward Gulski,Rogier Jongen,Aleksandra Rakowska,Krzysztof Siodla,.Offshore Wind Farms On-Site Submarine Cable Testing and Diagnosis with Damped AC. 12 (19),.
Select your report category*
Reason*
New sign-in location:
Last sign-in location:
Last sign-in date: